Compact requirements checklist

Tompkins Robotics RFQ Data Sheet for warehouse automation evaluations

A useful warehouse robotics RFQ states what the equipment carries, how often each route is demanded, where constraints occur, which control layer owns each decision and how performance will be accepted. This page reuses a compact compliance-style structure to capture those engineering facts—not sustainability slogans.

Requirements ledger

Capture facts, assumptions and open questions separately

Use one row per operating case when loads or routes differ materially. Attach source files, timestamps and owners so changes can be traced during design review with Tompkins Robotics.

Input groupMinimum informationWhy it changes the conceptPreferred evidence
Load unitLength, width, height, mass, center of gravity, underside, overhang, orientation and stabilityControls payload interface, braking, pickup tolerance and safe transferDimensioned drawing, weight range, representative samples
Material flowOrigins, destinations, moves by interval, SKU/order profile, replenishment, peak duration and cutoffDetermines mission demand, travel, queueing, buffer occupancy and fleet quantityTimestamped transaction extract and route matrix
Site geometryClear aisle width, turns, gradients, floor joints, doors, lifts, crossings, safety zones and charging areasDefines feasible paths, speed restrictions, traffic rules and intervention accessCurrent CAD, measured survey, marked photographs
Control interfacesWMS/WCS/WES/PLC/fleet-manager ownership, messages, acknowledgements, timeouts, alarms and network policyPrevents duplicated decisions, silent failures and unresolved exception statesResponsibility matrix, interface specification, sequence diagrams
AcceptanceDesign and peak rates, transaction definition, availability boundary, test duration, fault cases and evidence ownerTurns commercial expectations into repeatable FAT and SAT decisionsApproved protocol, scenario data, result and deviation template
Submission check

Before issuing the RFQ to Tompkins Robotics

01

Transaction is defined

The rate states exactly what completes a move, divert or order line, including pickup and drop confirmation.

02

Peak has a window

Demand identifies duration, recurrence, replenishment overlap and whether backlog is allowed.

03

Buffers are located

Every station and lane has a capacity, blocking rule and response when full or unavailable.

04

Interfaces have owners

Commands, data state, retries, alarms and manual decisions belong to named systems and teams.

05

Safety paths are visible

Pedestrian crossings, restricted areas, maintenance access and intervention points appear on the layout.

06

Failures are test cases

Blocked routes, host silence, network loss, low energy, lost load and disabled stations have expected outcomes.

Reference and certification boundaries

If the project cites ISO 3691-4, ISO 12100, ISO 13849-1 or a regional machinery regulation, specify whether each item is a design reference, product requirement, site integration obligation or requested third-party certificate. Do not use a framework name as a substitute for model-specific documentation. Tompkins Robotics will not treat a logo row as acceptance evidence.

For brownfield deployments, include cutover zones, allowed downtime, rollback steps, inventory reconciliation and temporary manual flow. For expansion, include the next expected destinations, workload range, charging capacity and network growth so the initial phase does not create avoidable constraints.

Reproducible acceptance example

Freeze the route map, robot configuration, interface version and test dataset before a run. Execute a named transaction mix for a stated duration, record completed and failed moves, queue time, buffer occupancy, energy state and recovery time, then repeat the same scenario after each material change. An example protocol requires a 120-minute nominal run followed by blocked-path, host-timeout and unavailable-station scenarios; the numbers are test conditions to approve, not Tompkins Robotics performance claims.

Technical trade-offs the RFQ must decide

Fixed automation versus flexible robotics. Fixed conveyors and sorters often deliver higher deterministic capacity for stable SKU mixes and known divert accuracy targets, but changeovers can be slower when destinations or packaging change weekly. Flexible AMR and AGV fleets usually phase into brownfield aisles faster and adapt layouts under volatile demand, yet they depend more on traffic rules, charging windows and exception recovery. State which outcome you prioritize: peak lines per hour under a frozen order profile, or reconfigurable routes with a documented system availability boundary.

Peak rate versus operational resilience. Headline moves-per-hour can conflict with buffer occupancy, redundancy and graceful degradation. A design that maximizes short peaks may starve recovery when a station is unavailable. Your RFQ should name the peak window length (for example 90 minutes), whether backlog is allowed, and the mean-time-to-repair assumption that still keeps outbound cutoffs intact.

Architecture comparison dimensions (not vendor scores). Compare AMR, AGV and sortation paths on the same axes: payload envelope (kg and mm), clear aisle width (mm), peak factor versus average, WMS/WCS/PLC ownership, charging or energy window, and recovery time after a blocked path. Tompkins Robotics uses these axes to decide whether a flexible fleet, a guided AGV loop or a hybrid with fixed induction is the honest concept—not a brochure feature list.

Known operating limits

Tompkins Robotics evaluations assume floor friction and joint quality allow the stated navigation mode; steep grades, soft floors or unmarked temporary obstacles can force speed derates. Shared aisles with forklifts require written priority rules before claiming concurrent throughput. Cold or wet zones may restrict battery chemistry, sensor performance and charging placement. These limits belong in the RFQ so SAT cases can exercise them instead of discovering them after go-live.

Send a compact, traceable requirements pack

Attach the route matrix, load evidence, site drawing, interface responsibility and draft acceptance scenarios. Mark unknowns clearly; they are inputs to resolve, not gaps to hide.